Punch List Report
The structure inspected is a new home. The items included on this Punch List Summary Report are items that have “not yet been completed”. Items, which are deficient or inoperative, are included on the Immediate Action or Attention Required Reports included above.
FLATROOF
3.1.0 FLAT
3.1.7 CANALES
SOME OF THE CANALES ARE CLOGGED WITH STUCCO DEBRIS ESPECIALLY ON THE EAST SIDE OF THE ROOF. ALL CANALES SHOULD BE CLEARED SO THAT THE ROOF CAN DRAIN PROPERLY. |
3.1.8 VENTS/COVERS
THE PARAPET VENT COVER ON THE NORTH SIDE OF THE HIGH ROOF HAS NOT BEEN INSTALLED. |